Project approval date: 2010-10-26
Project location: Kabul
Project description:
Construction of the association’s headquarters. The project is part of a football complex that includes an artificial turf pitch and a technical centre
Goal project number: 2
Project status: Active
Objectives:
The objectives of this project are:
-to deliver headquarters and administrative offices befitting a football association
-to improve the association’s training facilities
-to help the association to optimise the use of its headquarters
Goal contribution 400000
FAP contribution 175000
MA contribution 0
Other contribution 0
Total budget 575000
Contractors Total amount
Ehsanullah Timor Engineeing and Technical Services Company Ltd (ETESC) 5000
Peshsaaz Nawin Close Shareholding Construction Company 240022
Total paid 245022